This project consists of three phases:
- 19E Building
Pre-engineered building is complete with foundation, new slab on grade floors and includes 110,000 SF of manufacturing space, offices, restrooms, breakroom, truck dock, and a hazmat area with explosion relief panels. - North Manufacturing Building
A 125,000 SF conventional steel framed addition that will be used for manufacturing along with their tool and die department. - Administration Building
A 2-story, 45,000 SF building with a combination of conventional steel framing and pre-cast sandwich panel construction. This building uses specialized heating, cooling, and ventilation equipment. This building also features exposed structural ceilings, open / closed stairs, and polished concrete floors. This building includes a museum.